Schedule
The STEP project was officially launched in March 2017, and is a six-year government-industry collaboration with three distinct budget periods.
Budget period 1 (ends October 2018) Detailed Facility and Equipment Design (25 months) |
---|
|
|
|
|
|
Budget Period 2 (through 2024) Fabrication and Construction |
---|
|
|
|
Budget Period 3 (Planned for 2025-2026) Facility Operation and Testing |
---|
|
|
Become a project partner
This open project is welcoming new partners from around the world. OEMs, engineering companies, and power plant owner/operators are invited to join to gain a better understanding of how sCO2 technology can improve high-efficiency power generation.